As data center development accelerates, temporary or bridge-power generation is becoming an increasingly important option for facilities awaiting permanent utility connections. While these arrangements can help bring capacity online sooner, they also introduce air permitting requirements that may differ substantially from those governing emergency backup generators.
Recent Regulatory Developments
In August 2026, the North Carolina Department of Environmental Quality issued separate air permits for an Amazon data center project and Duke Energy Progress. Duke Energy's permit authorizes 57 temporary non-emergency diesel engines to provide bridge power until grid service becomes available, while Amazon's permit covers 588 emergency backup engines. The distinction reflects their different operating purposes and applicable requirements.
Other developments underscore the importance of proper equipment classification and permitting. In September, the New Jersey Department of Environmental Protection assessed a $1.07 million administrative penalty against DataOne for allegedly installing and operating 62 natural-gas generators without required permits. In Mississippi, an October federal court decision rejected an argument that trailer-mounted natural-gas turbines qualified for a mobile-source exclusion when denying a motion to dismiss a Clean Air Act lawsuit. That litigation remains ongoing.
Planning for Compliance from the Start
For data center developers and operators, these developments highlight the importance of evaluating temporary generation based on its actual equipment characteristics, intended operation, and applicable regulations. Physical mobility or a limited deployment period does not automatically exempt equipment from stationary-source permitting requirements.
Early coordination among facility owners, utilities, equipment providers, and environmental professionals can help establish permitting responsibilities, operating limits, monitoring requirements, and reliable documentation before temporary generation begins.
Temporary power may be a short-term solution, but environmental compliance must be considered throughout its operation.